Below are the projects that are planned to be implemented during 2019-2029:

  • Jvari-Khorga Project:
    • Construction of OHLs Odishi-1,2, Length: 60km;
    • Loop in/loop out of 500 kV OHL Kavkasioni to/from 500/220 kV SS Jvari, length 16 km (2x8km).
  • Batumi-Akhaltsikhe Project:
    • Installation of 2 bays in 500 kV SS Akhaltsikhefor 220 kV double-circuit OHL Batumi-Akhaltsikhe;
    • Construction of double-circuit 220 kV OHL Shuakhevi-Akhaltsikhe, Line length: 90 km;
    • Installation of 220/110 kV 125 MVA autotransformer in Shuakhevi.
  • Ksani-Stepantsminda-Mozdok Project:
    • Construction of 500 kV OHL SS Ksani – SS Stepantsminda, length – 100km;
    • Construction of 12.6 km section of Ksani –Stepantsminda, 133/166 section;
    • Construction of 500/110 kV SS Stepantsminda, installed capacity 250 MW;
    • Construction of 500 kV OHL from SS Stepantsminda till the border of Russia, length – 11 km.
  • Marneuli-Airum Project:
    • Construction of 500 kV OHL Marneuli – Ayrumi (to Armenian power supply system) length - 35.56 km (construction of new OHL of 18.56 km – from SS Marneuli 500 to Georgian-Armenian border).
  • Rehabilitation of 220 KV OHL Kolkhida-1
    • Rehabilitation of 220 kV OHL Kolkhida-1
  • Jvari-Tskaltubo-Akhaltsikhe Project:
    • Construction of 500 kV OHL Jvari – Tskaltubo, length - 76 km;
    • Construction of Double circuit design of 500 kV OHL Tskaltubo-Akhaltsikhe with the construction of single circuit, length 104 km;
    • Extension of 500 kV SS Akhaltsikhe, and arrangement of bay (to connect 500 kV OHL Tskaltubo – Akhaltsikhe);
    • Construction of 500/220 kV SS Tskaltubo (501 MW, 250 MW regulated reactor);
    • Construction of 500 kV OHL Tskaltubo-Zestafoni, length 30km;
    • Extension of 500 kV substationsZestafoni and Tskaltubo (to connect 500 kV OHLs Tskaltubo – Zestafoni and Tskaltubo – Akhaltsikhe);
  • North Ring – Tskaltubo Project:
    • Installation of 220/110 kV 63 MVA autotransformer and arrangement of 110 kV bays in Lajanuri HPP;
    • Construction of new 220/110 kV 250 MVA substation Lajanuri;
    • Construction of 220 kV OHL SS Lajanuri-Lajanuri HPP, length 1 km;
    • Construction of 2-circuit 220 kV OHL Oni-Lajanuri, length 55 km;
    • Construction of 500 kV OHL Lajanuri-Tskaltubo, length 49 km;
    • Construction of 2-circuit 220 kV OHL Kheledula-Lajanuri (operation on 110 kV), length 45 km;
    • Construction of 500/220/110 kV SS Nenskra, Installed capacity: 500 + 250 MVA;
    • Construction of 2-circuit 220 kV OHL Nenskra HPP-SS Nenskra, length 1 km;
    • Construction of 500 kV OHL Nenskra-Jvari, length 47 km;
    • Extension of 500 kV SS Jvari and arrangement of bays (to connect 500 kV OHL Jvari-Nenskra);
    • Construction of Double-circuit 110 kV OHL Nenskra-Mestia, length 57 km;
    • Loop in/Loop out of 500 kV OHL Kavkasioni to/from SS 'Nenskra, length 2 km;
    • Extension of 220/110 kV SS Lajanuri with 500 kV switchyard;
    • Loop in/Loop out of 2-circuit 220 kV OHL Kheledula-Lajanuri to/from HPPs Lentekhi and Tsageri, 2-2 km;
    • Construction of Double-circuit 110 kV OHL Lentekhi-Mukhra, length 12 km;
    • Construction of Double-circuit 110 kV OHL Mukhra-Luji, length 12 km;
    • Loop in/Loop out of 500 kV OHL Nenskra-Jvarito/from Khudoni HPP, length 1 km.
  • Guria Project:
    • Construction of 220/110 kV 250 MVA SS Ozurgeti wih the perspective of capacity increase;
    • Loop in/loop out of 220 kV OHL Paliastomi-1 to/from 220/110 kV SS Ozurgeti;
    • Construction of double-circuit 110 kV OHL Ozurgeti – Zoti HPP, length 49 km;
    • Construction of single-circuit 110 kV OHL Zoti HPP – Chokhatauri (existing substation), length 22 km, 110 MW capacity.
  • Akhaltsikhe-Tortumu Project:
    • Construction of 400 kV OHL Akhaltsikhe-Tortum; Length: 150 km (33 km to Georgia-Turkey border);
    • Extension of 500 kV SS Akhaltsihke and arrangement of bay (400 kV OHL Akhaltsihke-Tortum);
    • Construction of third 350 MW, 500/400 kV back-to-back link at SS Akhaltsikhe.
  • Batumi-Muratli Project:
    • Construction of One 350 MW, 220/154 kV back-to-back DC link and respective substations in Batumi;
    • Construction of 154 kV OHL Batumi-Muratli; Length: 15 km.
  • Namakhvani-Tskaltubo Project:
    • Construction of double-circuit (splitted conductor into two parts in each phase) 220 kV OHL Namakhvani-Tskaltubo (construction of 2nd circuit of OHL Derchi), length 24 km;
    • Construction of double-circuit (splitted conductor into two parts in each phase) 220 kV OHL Lower Namakhvani-Upper Namakhvani (construction of 2nd circuit of OHL Derchi), length 34 km.
  • Imereti Rehabilitation Project:
    • Rehabilitation of 500 kV Imereti OHL
  • Substations Renovation Project:
    • Construction of 220/110 kV substation Teleti, installed capacity 250MVA;
    • Loop in/loop out of 220 kV OHL Algeta (Navtlugi-Khrami 2 HPP) to/from SS Teleti;
    • Construction of 35 kV OHL Teleti-Shindisi;
    • Purchase/Installation of 2 x 200 MVA 220/110/10 kV autotransformers (existing and contracted) in SS Gldani-220;
    • Installation of 2 x 40 MVA 110/35/10 kV (contracted) transformers in SS Gldani220;
    • Purchase/installation of 110/35/6 kV 80 MVA (new) transformer in SS Navtlugi-220;
    • Installation of 2 x 40 MVA 110/35/6 kV transformers (One new, second one - moving from SS Didube-220) in SS Gardabani-500;
    • Purchase/installation of 2x63 MVA 110/35/10 kV (new) transformers in SS Gori-220;
    • Installation of new 110/35/10 kV 40 MVA (contracted) transformer in SS Gori-220;
    • Installation of new 2x200 MVA 220/110/10 kV (contracted) autotransformers in SS Kutaisi-220;
    • Installation of 110/35/6 kV 80 MVA (contracted) transformer in SS Didube-220;
    • Installation of 220/110/6 kV 125 MVA (moving from SS Gldani-220) autotransformer in SS Gori-220;
    • Installation of 220/110/10 kV 125 MVA (moving from SS Kutaisi-220) autotransformer in SS Tskaltubo-220;
    • Installation of 220/110/10 kV 125 MVA (moving from SS "Kutaisi-220") autotransformer in SS Menji-220;
    • Installation of 110/35/10 kV 25 MVA (moving from SS "Gori-220") transformer in SS Menji-220;
    • Purchase/installation of 2x80 MVA 110/35 kV (new) transformers with arrangement of respective bays in SS Khorga-220;
    • Purchase/installation of 220/110 kV 125 MVA (second) autotransformer with arrangement of respective bays in SS Gurjaani-220;
    • Purchase/installation of 220/110/10 kV 125 MVA (new) autotransformer with arrangement of respective bays in SS Batumi-220;
    • Installation of 2x40 MVA 110/35/10 kV (moving from SS Gori-220) transformers in SS Batumi-220;
    • 110 kV switchyard and purchase/installation of 2x63 MVA 220/110 kV autotransfermers in SS Akhaltsikhe-500;
    • 110 kV switchyard and purchase/installation of 2x63 MVA 220/110 kV autotransfermers in SS Jvari-500;
    • 110 kV switchyard and purchase/installation of 220/110/35 kV autotransfermers in SS Oni-220;
    • Renovation of 15 substations.
  • Kakheti Infrastructure Renovation Project:
    • Extension of SS Telavi-110 with 220 kV switchyard and purchase/installation of 220/110 kV 125 MVA Autotransformer;
    • Construction of double-circuit 110 kV OHL Telavi-Gurjaani, in 220 kV dimensions, length 45 km;
    • Loop in/loop out of one circuit of 110 kV OHL Telavi-Gurjaani to/from substations Tsinandali and Mukuzani;
    • Construction of double-circuit 110 kV OHL Telavi-Akmeta in 220 kV dimensions, length 38 km;
    • Rehabilitation of 220/110 kV SS Gurjaani;
    • Reconstruction of 110 kV substations Akhmeta, Tsinandali and Mukuzani;
    • Rehabilitaion of 110/35/10/6 kV equipment in Kakheti region;
    • Construction of 110 kV OHL Stori HPP-Telavi, length 49 km;
    • Construction of 220 kV OHL Akhmeta-Jinvali, length 58 km;
    • Construction of 220/110 kV substation in Jinvali.
  • Reactive power source (capacitor banks) Project:
    • Purchase/installation of 600 MVAR reactive power compensation equipment in 220 kV substations of Tbilisi.
  • Security of supply of Tbilisi region Project:
    • Loop in/loop out of 220 kV OHL Alaverdi to/from SS Marneuli-500, length 11 km;
    • 220/110 kV SS Norio, with 2x125 MVA installed capacity;
    • Loop in/loop out of 220 kV OHL Varketili to/from SS Norio-220, length 2x4 km;
    • Replacement of 500/220 kV 501 MVA autotransformer with 500/220 kV 801 MVA one in SS Ksani-500;
    • Construction of second circuit of 220 kV OHL Aragvi;
    • Construction of second circuit of 220 KV OHL Kukia.
  • Rehabilitation of 220 kV backbone Zestaponi-Ksani Project:
    • Rehabilitation of 220 kV OHL Surami, length 67 km;
    • Rehabilitation of 220 kV OHL Urbnisi, length 45 km;
    • Rehabilitation of 220 kV OHL Liakhvi, length 56 km.
  • Construction of second circuit of 330 kV OHL Gardabani-Agstafa Project:
    • Construction of second circuit of 330 kV OHL Gardabani-Agstafa, length 21 km (till Georgia-Azerbaijan border);
    • Purchase/installation of 330/220 kV, 400 MVA autotransformerin SS Gardabani.

For more details, you are encouraged to follow the link for the Ten Year Network Development Plan of Georgia: Ten Years Network Development Plan