Central SCADA System Software and Server Upgrade Project

The aim of upgrading the SCADA/EMS system is to ensure that hardware and software responds to modern system requirements, which implies the integration of new objects obtained as a result of electric network development, and, therefore, the processing of increased number of signals. In addition, the new system will be compatible with ENTSO-E standards.

The new high-level architecture of SCADA/EMS (Energy Management System) includes upgraded, transmission network management, monitoring and intellectual features of SCADA, also the Operator Simulator and Dynamic Stability Analysis (SIGUARD DSA) Module.

The upgraded hardware will improve the safe and reliable management process of the energy system.

The World Bank finances the project (Loan No 8377-GE). The Agreement on Transmission Grid Strengthening Project (№IDA/TGSP/DSI/DC/01-2017) was signed with the Austrian company SIEMENS AKTIENGESELLSCHAFT OSSREICH on 21 December 2017. To facilitate the project implementation, an agreement was signed with the supervisory consulting company PricewaterhouseCoopers Georgia LLC on 13 March 2015.

Project Status:

  • The design and planning phase is in progress.
  • The SCADA/EMS design-phase training has been conducted for GSE staff.
  • The design of hardware architecture has been agreed on.
  • The contractor has finished buying the equipment and started the configuration works.
  • The database migration to the new system is underway.

Duration of Project Implementation:

  • The project started on 22 December 2017
  • The estimated date of the project completion is 26 May 2020

Cost of the Project:

  • The project cost is EUR 2,819,918.45 (including VAT).

Project Team:

bela rexviashvili.jpg

Bela Rekhviashvili

Project Manager
Tel.: +995 32 2 510 202
E-mail: bela.rekhviashvili@gse.com.ge

nino lipartia.jpg

Nino Lipartia

Project Coordintor

Tel.: +995 32 2 510 202

E-mail: nino.lipartia@gse.com.ge