2014-06-24
Volume of Rehabilitation Works at PTL Paliastomi 1-2 has been Defined
Research works on power transmission lines damaged during the natural disasters of the past winter have been finalized. The volume of rehabilitation works to be performed on PTL Paliastomi 1-2 towers have been defined. The section of the line to be rehabilitated amounts to 70-80km. preparatory works have already been performed. Power transmission lines (East-West) rehabilitation team was created on the basis of regional approach. Vacancies have already been announced for the Western team. Simultaneously works are performed for the purpose of obtaining necessary materials in order to finalize the rehabilitation works by the winter season.
This will be the most large scale rehabilitation project for GSE, considering the complicated geographic location.
It should be noted that the Company plans to execute mentioned works with its own resources.